PSE&G solar interconnection: what it requires before you energize
How does PSE&G detect unpermitted backfeed?
Being verified being verified
What happens if they catch you?
Being verified being verified
Small and DIY interconnection requirements
Check their Solar Power Suitability Map first, it tells you whether your circuit can even take the system before you apply. Then a two-part application: part one before construction, part two after. documented
Precise clocks, from their own page: review confirmation within 3 business days, engineering determination within 18, approval or denial email within 21, and construction only after approval. After the UCC certificate: inspection outcome within 25 business days, meter swapped to bidirectional immediately on a pass, then the PTO notice authorizes turn-on. documented
Level 1 under 10 kW has no fee and no liability insurance requirement, the form says so explicitly. documented
The DIY catch: PSE&G's own FAQ answers the self-install question with a flat no, you must hire a solar contractor, even though the statewide NJ form contemplates owner-installers. Expect friction here that JCP&L doesn't give you. documented
Standard NJ 1:1 net metering, annual true-up pays leftovers at wholesale LMP. documented
sources: PSE&G solar application process · PSE&G Level 1 application (PDF)
Related: JCP&L (NJ) · Dominion Energy (VA)
Planning a zero-export or plug-in setup here? See the zero-export reality check and equipment notes.
Every claim above is evidence-graded: documented means it traces to the tariff or the utility's own filings, reported means a dated community report. The full table covers 53 utilities: see all of Gridrules.