JCP&L solar interconnection: what it requires before you energize
How does JCP&L detect unpermitted backfeed?
Being verified being verified
What happens if they catch you?
Being verified being verified
Small and DIY interconnection requirements
Level 1 under 10 kW, no fee, online portal, one-line diagram and site plan. No energizing before inspection and approval to operate. documented
Review answer in 10 to 30 days. JCP&L settings file required on UL1741-SB inverters. documented
NJ 1:1 net metering, annual excess paid at wholesale. documented
sources: NJ net metering & interconnection
Verify your export before JCP&L does
JCP&L nets your exports, but the meter still logs every reverse-flow interval, including ones you didn't plan. Worth knowing your real number before they do.
Clamp meter on the grid input · energy monitor on the export register
Building battery-first or zero-export anyway? Craftstrom · EZ-1 · EG4
Contains links to our partner sites. As an Amazon Associate we earn from qualifying purchases.
Related: PSE&G (NJ) · National Grid (NY (upstate))
Planning a zero-export or plug-in setup here? See the zero-export reality check and equipment notes.
Every claim above is evidence-graded: documented means it traces to the tariff or the utility's own filings, reported means a dated community report. The full table covers 60 utilities: see all of Gridrules.