Portland General Electric solar interconnection: what it requires before you energize
How does Portland General Electric detect unpermitted backfeed?
Being verified being verified
What happens if they catch you?
Being verified being verified
Small and DIY interconnection requirements
Level 1 for certified small systems, decision within 10 business days of a complete application, and PGE's own checklist recommends applying and waiting for approval before beginning any construction. documented
After install and local electrical inspection: send the signed agreement plus inspection proof, PGE site-inspects, swaps in a bidirectional meter, then issues permission to operate. documented
1:1 net metering up to 25 kW residential, monthly rollover, annual leftovers donated to low-income programs. PGE publishes a net metering capacity map, check your address before designing. documented
Battery quirk: non-export batteries need a signed letter stating the battery will not backfeed. documented
sources: PGE net metering capacity map · PGE interconnection process overview
Verify your export before Portland General Electric does
Portland General Electric nets your exports, but the meter still logs every reverse-flow interval, including ones you didn't plan. Worth knowing your real number before they do.
Clamp meter on the grid input · energy monitor on the export register
Building battery-first or zero-export anyway? Craftstrom · EZ-1 · EG4
Contains links to our partner sites. As an Amazon Associate we earn from qualifying purchases.
Related: Pacific Power (OR) · Dominion Energy (SC)
Planning a zero-export or plug-in setup here? See the zero-export reality check and equipment notes.
Every claim above is evidence-graded: documented means it traces to the tariff or the utility's own filings, reported means a dated community report. The full table covers 60 utilities: see all of Gridrules.