Portland General Electric solar interconnection: what it requires before you energize

OR · checked 2026-07-06 · request an update

How does Portland General Electric detect unpermitted backfeed?

Being verified being verified

What happens if they catch you?

Being verified being verified

Small and DIY interconnection requirements

Level 1 for certified small systems, decision within 10 business days of a complete application, and PGE's own checklist recommends applying and waiting for approval before beginning any construction. documented

After install and local electrical inspection: send the signed agreement plus inspection proof, PGE site-inspects, swaps in a bidirectional meter, then issues permission to operate. documented

1:1 net metering up to 25 kW residential, monthly rollover, annual leftovers donated to low-income programs. PGE publishes a net metering capacity map, check your address before designing. documented

Battery quirk: non-export batteries need a signed letter stating the battery will not backfeed. documented

sources: PGE net metering capacity map · PGE interconnection process overview

Related: Pacific Power (OR) · Dominion Energy (SC)

Planning a zero-export or plug-in setup here? See the zero-export reality check and equipment notes.

Every claim above is evidence-graded: documented means it traces to the tariff or the utility's own filings, reported means a dated community report. The full table covers 53 utilities: see all of Gridrules.