All 60 utilities / NV Energy
NV Energy solar interconnection: what it requires before you energize
How does NV Energy detect unpermitted backfeed?
Being verified being verified
What happens if they catch you?
Being verified being verified
Small and DIY interconnection requirements
Self-installation is explicitly allowed by the property owner in NV Energy's own handbook, they verify you are the owner. Application via the PowerClerk portal with one-line diagram, site plan, and equipment specs, plus a non-refundable fee. documented
No parallel operation before permission to operate. Completeness review within 10 business days, total time to PTO reported anywhere from 6-10 weeks to several months depending on project complexity. documented
AB 405 rates: new systems land in Tier 4, monthly netting with excess credited at 75% of retail, locked for 20 years at the install address. By law you can't size past 100% of your annual usage (highest 12 months of the past 24). documented
Fresh change: northern Nevada applications approved after Oct 1, 2025 get 15-minute netting instead of monthly, which cuts the value of midday exports. Existing customers keep their old structure. documented
sources: NV Energy solar handbook (PDF) · PUCN net metering tiers
Verify your export before NV Energy does
NV Energy nets your exports, but the meter still logs every reverse-flow interval, including ones you didn't plan. Worth knowing your real number before they do.
Clamp meter on the grid input · energy monitor on the export register
Building battery-first or zero-export anyway? Craftstrom · EZ-1 · EG4
Contains links to our partner sites. As an Amazon Associate we earn from qualifying purchases.
Related: Nolin RECC (KY (co-op))
Planning a zero-export or plug-in setup here? See the zero-export reality check and equipment notes.
Every claim above is evidence-graded: documented means it traces to the tariff or the utility's own filings, reported means a dated community report. The full table covers 60 utilities: see all of Gridrules.