Knoxville Utilities Board solar interconnection: what it requires before you energize

TN (TVA LPC) · checked 2026-07-09 · request an update

How does Knoxville Utilities Board detect unpermitted backfeed?

Being verified being verified

What happens if they catch you?

Being verified being verified

Small and DIY interconnection requirements

Municipal LPC under TVA, so the TVA framework row applies on top: no net metering exists, and exports only pay via TVA's Dispersed Power Production at avoided cost. documented

The number that stings: KUB charges a $500 application fee for any interconnection, stated plainly on their own page. That's twenty times what NorthWestern Montana charges for the same paperwork. documented

Sequence per local guidance: city or county electrical permit first, KUB interconnection approval after. KUB steers customers toward TVA's Quality Contractor Network and NABCEP-certified installers. documented

With avoided-cost-only exports and a $500 entry fee, the math here is self-consumption or nothing. Size small, use everything you make. documented

sources: KUB generate your own power · TVA dispersed power production

Related: Tennessee Valley Authority (TN + 6 states (153 LPCs)) · Sequachee Valley Electric Cooperative (TN (TVA LPC))

Planning a zero-export or plug-in setup here? See the zero-export reality check and equipment notes.

Every claim above is evidence-graded: documented means it traces to the tariff or the utility's own filings, reported means a dated community report. The full table covers 53 utilities: see all of Gridrules.