FPL solar interconnection: what it requires before you energize
How does FPL detect unpermitted backfeed?
Being verified being verified
What happens if they catch you?
Being verified being verified
Small and DIY interconnection requirements
Tier 1 under 10 kW: no application fee, no insurance requirement. Tier 2 above 10 kW requires proof of $1M liability. documented
Interconnection agreement and FPL approval before operating, meter swap after. documented
Florida has no plug-in solar law. documented
sources: FPL net metering
Verify your export before FPL does
FPL nets your exports, but the meter still logs every reverse-flow interval, including ones you didn't plan. Worth knowing your real number before they do.
Clamp meter on the grid input · energy monitor on the export register
Building battery-first or zero-export anyway? Craftstrom · EZ-1 · EG4
Contains links to our partner sites. As an Amazon Associate we earn from qualifying purchases.
Related: Tampa Electric (TECO) (FL (Tampa Bay)) · Georgia Power (GA)
Planning a zero-export or plug-in setup here? See the zero-export reality check and equipment notes.
Every claim above is evidence-graded: documented means it traces to the tariff or the utility's own filings, reported means a dated community report. The full table covers 60 utilities: see all of Gridrules.