CenterPoint Energy solar interconnection: what it requires before you energize

TX (Houston) · checked 2026-07-08 · request an update

How does CenterPoint Energy detect unpermitted backfeed?

Their own FAQ: turning on before PTO throws an error message on the smart meter and an employee investigates it documented

What happens if they catch you?

Same FAQ: early operation puts your account in violation status and delays your export data reaching your REP documented

Small and DIY interconnection requirements

Application via their eTRACK+ portal with one-line, site layout, and approved equipment models. Interconnection agreement signed, then PTO, then the meter is reprogrammed, then you may operate. documented

Self-installs are explicitly recognized: contractor jobs get photo-based visual inspection, DIY jobs get a scheduled onsite one. documented

Like Oncor: CenterPoint buys nothing, your REP handles buyback, and the smart meter reports excess in 15-minute intervals you can check yourself on smartmetertexas.com. documented

Lockable AC disconnect with external handle within 10 feet of the meter. documented

sources: CenterPoint DG application FAQ · PUCT rule 25.211 (PDF)

Related: Oncor (TX) · Austin Energy (TX (muni)) · PSEG Long Island (NY (LIPA))

Planning a zero-export or plug-in setup here? See the zero-export reality check and equipment notes.

Every claim above is evidence-graded: documented means it traces to the tariff or the utility's own filings, reported means a dated community report. The full table covers 53 utilities: see all of Gridrules.